Home Page
Info
Applications
Concrete required to fill tubes

As sold in bags by weight

DRY PRE-MIXED CONCRETE

1 ft. of 6" tube
=
32 lbs. (15 kg)
1 ft. of 8" tube
=
50 lbs. (23 kg)
1 ft. of 10" tube
=
82 lbs. (35 kg
1 ft. of 12" tube
=
115 lbs. (53 kg)
1 REDIBASE
=
260 lbs. (117 kg)

As delivered wet mixed by truck volume

WET MIXED CONCRETE

1 yd3
=
108 ft. of 6" tube 1 m.3
=
139 ft. of 6" tube
1 yd3
=
71 ft. of 8" tube 1 m.3
=
92 ft. of 8" tube
1 yd3
=
44 ft. of 10" tube 1 m.3
=
55 ft. of 10" tube
1 yd3
=
31 ft. of 12" tube 1 m.3
=
40 ft. of 12" tube
1 yd3
=
13-1/2 REDIBASES 1 m.3
=
17-1/2 REDIBASES

1 REDIBASE = 2 cu. ft. = .05664 cu. m.

Each Redibase form requires 8 - 10' tape to attach to tube

Any 1-1/2 to 2-1/2 tape will do but duct tape is best

Note: If necessary, after forms are placed and backfilled, concrete pour can be delayed several days (under dry to normal conditions).

Pour concrete before slump (ground settling) occurs.

Instructions
Installation
20 Common Questions
Frost Heave
Technical
Codes
Comparison
Contact